Type
Item
Estimated Time
Check with √ When Complete
Preparing for Upgrade
Check upgrade path
Obtain the latest aDeploy version
Prepare HCI update package
Check version information
Prepare license key
Read upgrade notes(in the release notes)
aSecurity Upgrade
Upgrade aSecurity before upgrading MGR
About 30 minutes
aNI Upgrade
Upgrade Network Insight (aNI) on HCI
HCI
Upgrade Process
Make sure there are no ongoing tasks
5 minutes
General page check
10 minutes
Health check
Environment check before upgrading HCI
Upload HCI update package/Verify software edition
3 minutes
Distribute update package
Packet size/Transfer rate-Packet size*2/Transfer rate
Pre-upgrade check
15 minutes
The larger the virtual storage capacity is, the longer the upgrade process takes.
Enable Maintenance Mode for the cluster
1 minute
Control plane active upgrade
25 minutes
Disable Maintenance Mode for the cluster
Live migration of VMs across nodes in the same cluster
3 minutes for each VM
The migration time of each VM varies according to the data volume and I/O status when the VM is running.
Enable Maintenance Mode for nodes
Related to the cluster size and workload.
Virtual storage active upgrade
Active upgrade for virtual network
Restart server manually
Disable Maintenance Mode for nodes
Repeat the preceding steps (starting from the live migration of VMs)
About 40 minutes for each node
Check business
30 minutes
License after upgrade