Preparing for Upgrade
Check upgrade path
Obtain the latest aDeploy version
Prepare HCI update package
Check version information
Prepare license key
Read upgrade notes(in the release notes)
aSecurity Upgrade
Upgrade to Security before upgrading MGR
About 30 minutes
aNI Upgrade
Upgrade Network Insight (aNI) on HCI
HCI
Upgrade Process
Make sure there are no ongoing tasks
5 minutes
General page check
10 minutes
Health check
Enable maintenance mode
1 minute
Environment check before upgrading HCI
Upload HCI update package/Verify software edition
3 minutes
Distribute update package
Package size * Number of nodes/Transfer rate
Pre-upgrade check
15 minutes. The time varies according to virtual storage capacity. The larger the storage capacity is, the longer the upgrade process takes.
Control plane active upgrade
11 minutes
VM active upgrade
5 seconds for every 5 VMs with vmTools installed.
2 minutes for each VM without vmTools installed.
Virtual storage active upgrade
Number of clustered nodes*10 minutes
Related to the scale and load of VMs
Active upgrade for virtual network
Apply new virtual storage version
Check business
30 minutes
License after upgrade